Monthly Archives: September 2018
Water Upgrade Week 4
The entirety of the remaining filters to be removed have been. Concrete work has begun. Concrete has been removed, concrete scored, forms erected, and structural rebar installed, It’s been another busy week at the water treatment facility. Additionally, a motor, … Continue reading
Water Upgrade Week 3
A LOT of activity occurred this last week. All filters to be removed have had their old media removed via vac-truck. Half of the tanks have been removed from the facility and all associated plumbing has been removed. Also, the … Continue reading
Water Upgrade Week 2
Four pressurized vessels were received this week. In addition, two electrical motors, one natural gas, and three vertical turbine pumps came to our community. Presently, 4 of 5 sand filters have been taken offline and are being prepped for removal. … Continue reading