Category Archives: Community

August 2019 Update

Posted in Updates | Comments Off on August 2019 Update

Town Newsletter July/2019

Posted in Updates | Comments Off on Town Newsletter July/2019

Memo- Roads

Posted in Updates | Comments Off on Memo- Roads

Memo- Taxes

Posted in Updates | Comments Off on Memo- Taxes

Summer Outdoor Watering Restriction Schedule

Beginning Thursday June 6, we will be implementing our regular summer outdoor watering restriction schedule which will be as follows: West side of Town (Bank side) Tuesdays, Fridays, and Sundays East side of Town (Co-op side) Mondays, Thursdays, Saturdays No … Continue reading

Posted in Announcements, Community | Comments Off on Summer Outdoor Watering Restriction Schedule

EMO Volunteers

Posted in Community | Comments Off on EMO Volunteers

Water Updates Week 10 & 11

Members from Sapphire were recently in Craik to install filter media into the 4 pressurized vessels. 16 ‘totes’ in total was installed over the course of several days. Each tote equating to approximately 1000 pounds. Further plumbing is presently being … Continue reading

Posted in Updates | Comments Off on Water Updates Week 10 & 11

Water Updates Weeks 8-9

Infrastructure work is the focus right now at the water plant. Several more transformers and electrical junction boxes have been installed. Much of the wiring tray has been installed and some cabling completed. Further, actuated valves have been installed on … Continue reading

Posted in Announcements, Updates | Comments Off on Water Updates Weeks 8-9

Water Upgrade Weeks 5-7

The water plant is no stranger to contractors these days. The concrete pads have been filled and cured. Four pressurized tanks have been installed. One electric motor and vertical turbine pump installed. Variable Frequency Drives (VFDs) have been installed and … Continue reading

Posted in Community, Updates | Comments Off on Water Upgrade Weeks 5-7

Water Upgrade Week 3

A LOT of activity occurred this last week. All filters to be removed have had their old media removed via vac-truck. Half of the tanks have been removed from the facility and all associated plumbing has been removed. Also, the … Continue reading

Posted in Updates | Comments Off on Water Upgrade Week 3