Category Archives: Updates
Water Updates Week 10 & 11
Members from Sapphire were recently in Craik to install filter media into the 4 pressurized vessels. 16 ‘totes’ in total was installed over the course of several days. Each tote equating to approximately 1000 pounds. Further plumbing is presently being … Continue reading
Water Updates Weeks 8-9
Infrastructure work is the focus right now at the water plant. Several more transformers and electrical junction boxes have been installed. Much of the wiring tray has been installed and some cabling completed. Further, actuated valves have been installed on … Continue reading
Water Upgrade Weeks 5-7
The water plant is no stranger to contractors these days. The concrete pads have been filled and cured. Four pressurized tanks have been installed. One electric motor and vertical turbine pump installed. Variable Frequency Drives (VFDs) have been installed and … Continue reading
Water Upgrade Week 3
A LOT of activity occurred this last week. All filters to be removed have had their old media removed via vac-truck. Half of the tanks have been removed from the facility and all associated plumbing has been removed. Also, the … Continue reading
Water Upgrade Week 2
Four pressurized vessels were received this week. In addition, two electrical motors, one natural gas, and three vertical turbine pumps came to our community. Presently, 4 of 5 sand filters have been taken offline and are being prepped for removal. … Continue reading
2017 Drinking water quality and compliance report
2017 Craik -Drinking Water Quality and Compliance